In the Beginning: Winter 2007
Week of Oct. 1, 2007: Land Clearing Started
Week of Oct. 15, 2007: Clearing continues, initial steel building components arrive
Week of Oct. 29, 2007: Ground Breaking w/Mayor, slab area graded, foundations started
Week of Nov. 19, 2007: Foundation walls and column pads continue, site work continues
Week of Dec. 3, 2007: Building Steel Erection Started
Week of Jan. 1, 2008: First 200' of Building Steel Framing Completed
Week of Feb. 18, 2008: Rear Foundations completed, clear span section of building started
Week of Mar. 17, 2008: clear span overhead girders being erected as building grows
Week of April 14, 2008: Work picks up on building interior as weather improves
Week of May 12, 2008: Progress continues on building, entrance, and fields
Week of June 16, 2008: Floor poured for courts and front field as work progresses
Week of July 14, 2008: Indoor fields being prepped, outdoor fields cleared and being graded
Week of Aug 25, 2008: Indoor synthetic grass fields installed, outdoor fields final grading
Week of Sept 15, 2008: Indoor Fields, Boarded Field, Gym courts & Outdoor Field Lights, field one ready to be turfed
Week of Oct. 13, 2008: Building & front landscape, Boarded Field Turfed, 4 lined grass fields and interior
Week of Nov. 23, 2008: Building complete and ready to open, outdoor field turf installation progresses